| Programming/Site Investigation | June 2008 - February 2009 |
| Program Redefinement and Concept Development | October 2008 - March 2009 |
| Schematic Design | January 2009 – June 2009 |
| Schematic Design Drawings | June 2009 |
| Design Development | June 2009 – October 2009 |
| Cost Estimate | September 2009 – October 2009 |
| Construction Documents | July 2009 – February 2010 |
| Demolition of Kendall Hall | September 2009 – December 2009 |
| Groundbreaking | December 2009 |
| Construction | December 2009 – June 2011 |
| Construction Complete/Occupancy | July 2011 |